chaudhary0701 said:I got ppr does it means that i got PR???????
. AOR 19 aug (approx) done it thru consultant dats why not sure abt date.yes i frm indiasunil55 said:Hey CONGRATS.
when did u get AOR Are u outlander from India??
WHICH NOC
chaudhary0701 said:. AOR 19 aug (approx) done it thru consultant dats why not sure abt date.yes i frm india
Anya654 said:You submitted on August 19 and got PPR September 04 that means the whole process took 2 weeks and 2 days!! Unfortunately I still find that hard to believe because criminal and security checks alone take at least a month to complete and they won't even start these until your medical has passed. Please when did your medical pass and did you actually receive the PPR letter or a decision made status on ECAS?
chaudhary0701 said:They recvd application 19 Aug
sent correspondence acknowledging receipt of your application(s) on August 19, 2015.
they started processing your application on August 20, 2015
24 August Schedule A requested
25 August Schedule A submitted
27 Aug acknowledging receipt
Sept 4 Passport request. They mention in letter submit within 30 days thru VFS.
This is from my ECAS.
Thanks
chaudhary0701 said:They recvd application 19 Aug
sent correspondence acknowledging receipt of your application(s) on August 19, 2015.
they started processing your application on August 20, 2015
24 August Schedule A requested
25 August Schedule A submitted
27 Aug acknowledging receipt
Sept 4 Passport request. They mention in letter submit within 30 days thru VFS.
This is from my ECAS.
Thanks