Timeline:

Montreal, Quebec
Application submitted: 16th Oct 2011
Acknowledgment: 29th Oct 2011
Booklet received: 6th Nov 2011
Processing started: 10th Nov 2012
Still has status " In process"

Does anyone know how long it will take after In-process status for test?
 

Min Fu

Newbie
Apr 22, 2013
5
0
My application is also in Montreal. I submitted in July 2011. My application started in process in July 2012, and I was called first time for the test in Dec 2012, but skipped and haven't get any response since then.

Good Luck
 

EasyRider

Hero Member
Oct 12, 2008
431
18
Montreal
Job Offer........
Pre-Assessed..
You may expect to get test notice any day.

Usually, it's 19-20 months from application date to test.

Check Montreal timeline: https://docs.google.com/spreadsheet/lv?key=0Ai9o70015IRPdFl6MnhXV0VZbnN1YnZWLXpld0Vya1E&type=view&gid=4&f=true&colid0=1&filterstr0=Montr%C3%A9al&sortcolid=-1&sortasc=true&rowsperpage=250
 

Canuck2b

Member
Nov 29, 2011
19
0
I will be attending the Oath ceremony on Sept 6th in Montreal. The entire process took 23 months.
I had my exam the last week of May.

Good luck to everyone.
 

FL1040

Hero Member
Dec 30, 2013
260
10
Montreal
Job Offer........
Pre-Assessed..
Application sent April 8, 2013

Application processing started on June 7, 2013

Residence Questionnaire received on October 4, 2013

Notice to prepare for test received on December 28, 2013
 

lolo123

Newbie
Dec 31, 2013
2
0
Since you did the test will you tell us what happened did you pass? did they told you when is the citizenship oath is going to be!!

FL1040 said:
Application sent April 8, 2013

Application processing started on June 7, 2013

Residence Questionnaire received on October 4, 2013

Notice to prepare for test received on December 28, 2013
 

FL1040

Hero Member
Dec 30, 2013
260
10
Montreal
Job Offer........
Pre-Assessed..
lolo123 said:
Since you did the test will you tell us what happened did you pass? did they told you when is the citizenship oath is going to be!!
I have not taken the test yet..just got the notification to get ready for it last week..it might take a year, but if I have the hunch that things are speeding up, I have a friend who applied in 2012 and it took him 7 months to get a notification saying they had received the application, in my case it was only 3 months. My friend, by the way, is still waiting for anything to happen.
 

citizen_jr

Newbie
Jan 3, 2014
3
1
Application sent November 2012

Application processing started on Jan 2013

Residence Questionnaire received on September 2013

Test Data Received on Jan 2014, test date is Feb 13 2014

So things do seem to be speeding up. I was expecting to wait at least 12 months after sending the RQ to hear any news, it only took 2. Mine's a pretty straightforward case, though.
 

FL1040

Hero Member
Dec 30, 2013
260
10
Montreal
Job Offer........
Pre-Assessed..
flybest1 said:
RQ , I am at 34 months since application. Montreal office...don't know what do to...

Give them a call, my experience calling CIC has always been good, it takes a while to connect to an operator but oce you do they are very polite and give you reasonable answers..34 months is way to long
 

QC123

Newbie
Nov 10, 2011
6
0
sent application for citixenship aug 2012...
in process sept 2012 and received booklet...
fingerprinting requested mid oct 2013 by local cic montreal...
have done the prints digitally and been received by cic oct 22nd 2013 by local cic...
received test date to be jan 31, 2014...
 

FL1040

Hero Member
Dec 30, 2013
260
10
Montreal
Job Offer........
Pre-Assessed..
QC123 said:
sent application for citixenship aug 2012...
in process sept 2012 and received booklet...
fingerprinting requested mid oct 2013 by local cic montreal...
have done the prints digitally and been received by cic oct 22nd 2013 by local cic...
received test date to be jan 31, 2014...
Where did you go or the digital fingerprints?

Thanks
 

Donizinho

Star Member
Apr 3, 2013
54
1
Job Offer........
Pre-Assessed..
Family Application sent October, 2011

Application processing started on December, 2012

Residence Questionnaire received on April, 2013

Notice to prepare for test received on December 11, 2013

27 months since the beginning...
 

dafunk

Newbie
Aug 16, 2013
6
0
FL1040 said:
Application sent April 8, 2013

Application processing started on June 7, 2013

Residence Questionnaire received on October 4, 2013

Notice to prepare for test received on December 28, 2013


dear FL1040
I just got an RQ; after you filled the questionnaire and sent, did you have to see a judge or they just reviewed your questionnaire and gave you a decision by mail?